Lot 40 - Ravello Rise


Lot 40 - Ravello Rise

Friday, September 3, 2010

Week 5

View of Ravello Rise from the North East

The first floor frames have been completed and the floor joists for the second floor have begun to be installed.


Installing the floor joists, we were able to get a preview of the great view over the valley to the south from the second floor.

Installing floor joists.
View of the back of the house
Building paper for the first floor went on towards the end of the week.



Another good week at Ravello Rise, next week we hope to have the second storey floor completed!