Lot 40 - Ravello Rise


Lot 40 - Ravello Rise

Sunday, August 22, 2010

Week 3


We had quite alot of rain this week on Ravello Rise. Despite this, the concrete slab has been completed, drains and services have been installed and the site is in the process of being tidied up for construction to commence.

Foundations ready for concrete
Concrete just after it was poured.
Getting ready to put in drains and services.

Concrete slab complete. Next week, frames!