Lot 40 - Ravello Rise


Lot 40 - Ravello Rise

Friday, August 27, 2010

Week 4

This week the frames for the bottom floor arrived and were stood. The steel beams arrived towards the end of the week and were installed on Friday morning.

 
  
The rain eased this week allowing the site to dry out, which was good.


The frames went up without a hitch and fit together perfectly thanks to the precise work of our foundation team, chippie and timber supplier!


Steel beams were installed on Friday morning. 


 

At the end of the first month of construction at Ravello Rise we are pretty happy with the progress of Lot 40.

Sunday, August 22, 2010

Week 3


We had quite alot of rain this week on Ravello Rise. Despite this, the concrete slab has been completed, drains and services have been installed and the site is in the process of being tidied up for construction to commence.

Foundations ready for concrete
Concrete just after it was poured.
Getting ready to put in drains and services.

Concrete slab complete. Next week, frames!

Friday, August 13, 2010

Week 2


Beautiful weather going into week 2 of the build.


With retaining work done, this week we are hoping to complete the underfloor insulation and steel reinforcing for the concrete block. 

Insulation and steel going in.

 

Rain predicted over weekend... we are again hoping for good weather next week as we will be pouring concrete!

Saturday, August 7, 2010

First week onsite.


Site has been cut and flattened. Driveway crossing has also been cut.


Blocks at rear of house laid.


Views of land across the street and of Ravello Rise itself.



Have had quite a bit of rain this week, hoping for better weather next week!
 

Welcome to our Blog!


Work on this new 5 bedroom house commenced on 2 August 2010.

We will be keeping an online journal of our progress over the coming months. 
Thanks for your interest!