This week the frames for the bottom floor arrived and were stood. The steel beams arrived towards the end of the week and were installed on Friday morning.
The rain eased this week allowing the site to dry out, which was good.
The frames went up without a hitch and fit together perfectly thanks to the precise work of our foundation team, chippie and timber supplier! |
Steel beams were installed on Friday morning.
At the end of the first month of construction at Ravello Rise we are pretty happy with the progress of Lot 40.