Lot 40 - Ravello Rise


Lot 40 - Ravello Rise

Friday, October 29, 2010

Week 13

Brilliant weather at Ravello Rise this week!


Inside, central vacuum and gas pipes were installed...

Outside, the weatherboards have now been finished and will be painted next week.

 

Sunday, October 24, 2010

Week 12

This week the bricks were laid...


and the weatherboards have started to be installed.


Inside, our plumber has complete the pipe work and the stairs have arrived...


We hope to complete the house in early December.

Monday, October 18, 2010

Week 11

This week, the garage door arrived, the roof gutters were completed, a temporary front door lock was fitted and the soffits have been completed.


The bricks have also arrived this week and will be laid starting next week.

Saturday, October 9, 2010

Week 10

This week, the windows and front door went in and the top roof was completed.


The roof gutters are in and plumbing has also begun to be installed.


For the next few weeks we will be working on the exterior cladding.

Sunday, October 3, 2010

Week 9

This week the upper roof trusses were completed, fascia was installed and scaffolding arrived.


We have put plywood on the lower roof to ensure that the roof stays in pristine condition and won't get damaged from being walked on.

 
Next week we aim to complete the roof and have all windows and doors installed.